Activity I: An activity on the critical path of a project was scheduled to be completed within 12 weeks, with a budget of $8,000. During a performance review, which took place 7 weeks after the activity was initiated, it was found that 50% of the work had already been completed and that the actual cost was $4,500.
Calculate the EV of the activity.
Calculate the CI and SI for the activity.
Calculate the expected BAC using the original estimate approach.
Calculate the expected BAC using the revised estimate approach.
Compare and discuss the results obtained in parts (c) and (d).
Activity II: Identify a new product that is based on an innovation in technology, and draw up a strategic technical plan for its development. Be sure to discuss the risk factors at each stage, and indicate how you would deal with each.
Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.
You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.
Read moreEach paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.
Read moreThanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.
Read moreYour email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.
Read moreBy sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.
Read more